Another investment in Gippsland's future completed
Following the completion of Longford’s $1 billion Gas Conditioning Plant in May this year, Esso is pleased to mark yet another milestone in our ongoing investment into our Gippsland operations. On 1 October 2017, the first crude oil arrived at our Long Island Point facility in Hastings through our new $400 million pipeline from Longford.
News
Another investment in Gippsland's future completed
The new pipeline is a vital piece of infrastructure which will help to ensure reliable, affordable gas and petroleum products continue to flow to Australian households and businesses.
The project involved replacing the original 187 kilometre crude oil and condensate pipeline between our Longford and Long Island Point plants.
The real challenge for this project lay in its location, crossing more than 300 individual landowners’ properties. From the start we engaged with landowners to ensure we mitigated potential impacts on their properties. We thank each and every one of them for their patience and understanding as we completed this important work.
The construction teams also went to great lengths to minimise the projects impact on the environment and disruption to the broader community. This included using horizontal directional drilling technology to go under railways, as well as major and minor roads. We also partnered with Conservation Volunteers Australia and Landcare to deliver environmental projects along the pipeline route.
In our many years of operations across Gippsland, Esso has a strong track record of supporting local contractors and suppliers. Overall Australian labour, materials and equipment made up around 90% of the project spend. At its peak, the project employed over 450 people, with many local to Gippsland.
Our construction contractor, Nacap, also engaged a number of local suppliers in the Gippsland region and along the pipeline route, for a variety of products and services.
But it’s more than just the materials and equipment, it’s the flow on indirect benefits to the communities we worked in. It’s the early morning coffees we bought in Warragul, or the comfortable beds our teams slept in Morwell when they were away from home.And we thank you for making us feel at home.
To deliver a project of this magnitude requires the ongoing support of landowners and it has shown us how vital it is that we take the community with us every step. We recognise that there is still some work to do and we’re committed to completing this work as quickly and efficiently as possible.
The fact that this project was delivered ahead of schedule and within budget, and with every effort made to cause minimal disruption to the community, delivers a tremendous boost to our ability to compete for capital investments for future projects.
With continued investment in our operations, we’ll maintain the quality jobs in the region and the flow on benefits to the Gippsland region.
Related content

Offshore Wellness Initiative targets health and wellbeing across the Gippsland Basin
120 participants across offshore receive tailored programs to support their physical and mental healthEsso news Article •

Esso's aircraft stuns at the Sale ANZAC Weekend Airshow
An Esso Australia helicopter featured in a line-up of impressive aircrafts over the long weekendEsso news Article •

Foodbank Victoria Farms to Families
Pop-up market a success in Sale thanks to Esso Australia employees!Esso news Article •

Kiteboard for Life Australia visits the team at LIP
Maintaining a positive mindset and prioritising mental health in the workplaceEsso news Article •

Esso supports the Sale Music Festival
Sun shines for the free, family friendly event over the Labour day weekendEsso news Article •

More apprentices kick start their careers with Esso Australia
Esso Australia welcomes eight new apprentices to the team across the Longford and Long Island Point plantsEsso news Article •