Loading arm removal a success at LIP

The removal of a marine loading arm at Esso’s Long Island Point (LIP) Plant proved a logistical challenge that the team involved were able to successfully solve, with the arm removed safely during recent works at site.

News

Two mobile cranes were required for the removal. A 220 tonne crane was used for the main lift and a 90 tonne tailing crane was used to rotate the loading arm and load onto the truck bed. The total lift weight was around 17,000 kilograms – a massive undertaking!

LIP Project Engineer Samantha Stevenson said that while the LIP Plant berthing head accommodates eight marine loading arms, current arm numbers one and three are used for LPG loading and arm numbers seven and eight are used for crude oil loading.

“Loading arms two, four, five and six are no longer required for ship loading and have been out of service for several years, and arms four, five and six were removed in an earlier project. 

“Arm two was of a different design to the previously removed arms and is located between two in service loading arms, making the eccentrically loaded lift much more complicated and the timing extremely sensitive to external factors, such as wind,” she explained.

While the project presented a number of logistical and engineering challenges to be worked through ahead of the removal, it was completed safely and successfully, with the arm transported offsite, dismantled into smaller parts and taken to metal recyclers.

“It’s great that the metal from the arm will be able to be repurposed for future use. Most importantly, the project was completed safely and represents a great technical success story for the team at LIP,” she concluded.

 

Related content


Playing a vital role in emergency response preparedness

Playing a vital role in emergency response preparedness

In September, ExxonMobil Australia held an exercise with the ExxonMobil Regional Response Team (RRT) at our Docklands office. More than 65 participants across our different sites came together and tested their knowledge and competency skills for oil spill preparedness over a span of two days

Esso news Article

ExxonMobil Australia recognised for contribution towards TAFE Gippsland scholarships program

ExxonMobil Australia recognised for contribution towards TAFE Gippsland scholarships program

Recently, TAFE Gippsland held a recognition event to thank ExxonMobil Australia for our generous contribution towards their ongoing scholarships program. ExxonMobil Australia Chair, Dylan Pugh, along with TAFE Gippsland's CEO, Laura Macpherson, presented scholarship awards to four recipients who will now be able to pursue their studies and further develop their skills thanks to our contribution.

Esso news Article

2023 is proving to be a busy year for the Wells team!

2023 is proving to be a busy year for the Wells team!

Hear from Ryan Turton, Wells Operations Superintendent, on the latest projects and achievements by the Wells team including their recent milestone of 100 wells plugged and abandoned.

Esso news Article

2023 Reservoir Management Seminar

2023 Reservoir Management Seminar

The 2023 Reservoir Management Seminar was held at ExxonMobil’s Houston Campus last month.

Esso news Article

Sustainably improving process safety at our Longford Plants

Sustainably improving process safety at our Longford Plants

The Alarm System Structural Improvement & Sustainment Team (ASSIST) recently made changes to process alarms and reduced the number of standing alarms on each panel at the Longford site.

Esso news Article

"You can't be what you can't see": Blazing the way for female engineers

What does it take to be a STEM superstar at ExxonMobil, one of the world's largest petroleum and petrochemical company? Meet Caitlyn Broberg and discover how science, exercise and art have powered her life.

Esso news Article