Another investment in Gippsland's future completed

Following the completion of Longford’s $1 billion Gas Conditioning Plant in May this year, Esso is pleased to mark yet another milestone in our ongoing investment into our Gippsland operations. On 1 October 2017, the first crude oil arrived at our Long Island Point facility in Hastings through our new $400 million pipeline from Longford.

The new pipeline is a vital piece of infrastructure which will help to ensure reliable, affordable gas and petroleum products continue to flow to Australian households and businesses.

The project involved replacing the original 187 kilometre crude oil and condensate pipeline between our Longford and Long Island Point plants.

The real challenge for this project lay in its location, crossing more than 300 individual landowners’ properties. From the start we engaged with landowners to ensure we mitigated potential impacts on their properties. We thank each and every one of them for their patience and understanding as we completed this important work.

Image Photo Esso has completed the construction of a 187 kilometre pipeline that runs from our Longford Plants to our Long Island Point facility in Hastings: The new pipeline is a vital piece of infrastructure, which will help to ensure reliable, affordable gas and petroleum products continue to flow to Australian households and businesses.
Photo — Esso has completed the construction of a 187 kilometre pipeline that runs from our Longford Plants to our Long Island Point facility in Hastings: “The new pipeline is a vital piece of infrastructure, which will help to ensure reliable, affordable gas and petroleum products continue to flow to Australian households and businesses.”

The construction teams also went to great lengths to minimise the projects impact on the environment and disruption to the broader community. This included using horizontal directional drilling technology to go under railways, as well as major and minor roads. We also partnered with Conservation Volunteers Australia and Landcare to deliver environmental projects along the pipeline route.

In our many years of operations across Gippsland, Esso has a strong track record of supporting local contractors and suppliers. Overall Australian labour, materials and equipment made up around 90% of the project spend. At its peak, the project employed over 450 people, with many local to Gippsland.

Our construction contractor, Nacap, also engaged a number of local suppliers in the Gippsland region and along the pipeline route, for a variety of products and services.

Image Photo The construction teams went to great lengths to minimise the projects impact on the environment and disruption to the broader community.
Photo — The construction teams went to great lengths to minimise the projects impact on the environment and disruption to the broader community.

But it’s more than just the materials and equipment, it’s the flow on indirect benefits to the communities we worked in. It’s the early morning coffees we bought in Warragul, or the comfortable beds our teams slept in Morwell when they were away from home.And we thank you for making us feel at home.

To deliver a project of this magnitude requires the ongoing support of landowners and it has shown us how vital it is that we take the community with us every step. We recognise that there is still some work to do and we’re committed to completing this work as quickly and efficiently as possible.

The fact that this project was delivered ahead of schedule and within budget, and with every effort made to cause minimal disruption to the community, delivers a tremendous boost to our ability to compete for capital investments for future projects.

With continued investment in our operations, we’ll maintain the quality jobs in the region and the flow on benefits to the Gippsland region.

Image Photo Overall Australian labour, materials and equipment made up around 90% of the pipeline project spend. At its peak, the project employed over 450 people, with many local to Gippsland.
Photo — Overall Australian labour, materials and equipment made up around 90% of the pipeline project spend. At its peak, the project employed over 450 people, with many local to Gippsland.

Related content

Intern profile - Ebony Dodemaide

Intern profile - Ebony Dodemaide

Meet Ebony Dodemaide, intern for ExxonMobil Australia’s Upstream Commercial team. She’s one of 15 individuals selected amongst a pool of more than 600 applicants for our internship program this year.
Team members recognised through ExxonMobil's Engineering Workforce Credentialing Program

Team members recognised through ExxonMobil's Engineering Workforce Credentialing Program

Last month, team members were recognised for achieving Fellow and Engineering Executives statuses through ExxonMobil’s Workforce Credentialing Program.
Celebrating NAIDOC Week

Celebrating NAIDOC Week

This year’s theme, Keep the Fire Burning! Blak, Loud and Proud, recognises the unyielding spirit of our Aboriginal communities and enables them to keep their voices and culture alive and strong.
Building leadership capabilities through adequate training

Building leadership capabilities through adequate training

At ExxonMobil Australia, we place great emphasis on leadership training, ensuring our employees are provided adequate training and resources to help them smoothly transition into supervisory or leadership roles.
Employee profile - Margaret Rogacki

Employee profile - Margaret Rogacki

From an intern working in Gippsland on Barracouta platform projects in 1998 to Vice-Chair of the Asia Natural Gas and Energy Association in 2024, hear how Margaret Rogacki, General Manager - Australia LNG, has grown her career throughout the years.
Longford Quarterly Update - June 2024

Longford Quarterly Update - June 2024

In this update to our Longford Plants neighbours, Manager Clinton Gentle, highlights decommissioning works in Bass Strait.