Safely changing Altona’s outlook

On a still day in September, the Altona skyline was changed with the removal of the top of the refinery’s 100-metre Thermofor Catalytic Cracker (TCC).

When it was built in the mid ’50s the TCC was the tallest structure in Melbourne.

The tower’s catalytic cracking refining technology was developed by ExxonMobil affiliates during World War II. It changed the refining industry and allowed the production of 100 octane aviation fuel in large quantities, a key factor in supporting the Allied success.

Altona’s TCC was the first of its kind in Australia. It was decommissioned in 1997 when it was replaced with newer, more efficient technology, the Fluidised Catalytic Cracker.

“As we renew the refinery, we need to reclaim the area it takes up so we can put it to better use,” explained the Refinery Maintenance, Reliability and Engineering Manager Andrew Williamson.

The project team began the demolishing work last July.

“To remove the tower itself we are using the World’s largest, free-standing, luffing-jib tower crane,” said Senior Project Manager Paul McNamara. “One of our key tasks in planning the TCC demolition back in 2014 was relocating a family of peregrine falcons.

“Although they had nested in several locations around the refinery, their favourite spot was on the surge separator at the top of the TCC.

“We consulted Victorian Peregrine Project Manager Victor Hurley who recommended a new nesting box on a larger chimney nearby.

“Using design drawings provided by Victor, we installed the new nesting box in 2015 halfway up the chimney with the peregrines’ favourite southeasterly view over the city skyline.”

Image Photo— The tower crane starts to dismantle the TCC.
Photo — The tower crane starts to dismantle the TCC.

On September 9 the TCC Removal Team were able to take advantage of still weather to safely lift the 125 tonne surge separator off the top of the TCC.

“By the end of September we were able to remove the most visible components of the tower slightly ahead of schedule,” said Paul.

“This was a significant milestone as it has reduced the overall risk-profile of the task. However, the coming weeks and months still present significant challenges for the team as we move into the next phase of works.”

Project Executive David Young said that removing the TCC from an operating refinery was a complex engineering endeavour.

“In safely executing what is an intricate, multifaceted demolition job all project personnel have worked impressively as a cohesive unit,” he said.

“We have received excellent support and collaboration from the refinery operations team throughout the extensive planning stage and project execution.”

The Altona Refinery Manager Riccardo Cavallo presented the contractor, McMahon Services, the annual award for Commitment to Continued Safety Performance Improvement.

With the TCC tower gone, this was the peregrine falcon’s first breading season without their favourite nest site.

“I can’t tell you how pleased we all when a drone filmed three grown chicks in their new home,” said Paul.

“On a dollar-per-square-metre basis, this would have to be one of the most expensive apartments in Melbourne.”

Image Photo — A drone picture of the peregrines in their new home. “In safely executing what is an intricate, multifaceted demolition job all project personnel have worked impressively as a cohesive unit.”
Photo — A drone picture of the peregrines in their new home. “In safely executing what is an intricate, multifaceted demolition job all project personnel have worked impressively as a cohesive unit.”

Rekated content

"Each day brings a new challenge"

Birkenhead Terminal and Adelaide Airport Manager Aaron Bandy shares the exciting development opportunities he has been offered throughout his Mobil career.
Lighting up an iconic landmark in the Williamstown skyline

Lighting up an iconic landmark in the Williamstown skyline

Seaworks Maritime Museum has installed LED lighting in the historical Gellibrand Pile Light thanks to Mobil’s latest contribution.
Mobil Altona Terminal team celebrates completion of multiple major project milestones

Mobil Altona Terminal team celebrates completion of multiple major project milestones

The completion of a complex integrated event, achieving multiple major project milestones was celebrated with a special lunch at the Altona site.
ExxonMobil Australia's new Chair tours Mobil's Melbourne Terminal

ExxonMobil Australia's new Chair tours Mobil's Melbourne Terminal

New Chair Simon Younger recently toured some of the business’ midstream facilities in Victoria as part of his introduction to the company’s Australian operations.
Mobil Oil Australia's 2024 Retail Conference

Mobil Oil Australia's 2024 Retail Conference

The Mobil team was proud to host its second annual Retail Conference at Crown Metropol Melbourne where they launched the next generation of Mobil Fuels.
Yarraville Terminal commissions new control room

Yarraville Terminal commissions new control room

The control room’s new location brings operators, management and support services together, forming a winning competitive team, as we continue our transition to one Melbourne Terminal.